Miraka Powder Project

The Brief

To be built on a green filed site in Taupo.

Ebert Construction was the main contractor to carry out this project.

Industrial Surefloors were contracted by Ebert’s to complete the flooring works on the site.

The Solution

    • Sureshield Flooring
    • Surechem VE Flooring
    • Situclad VE Glass Flake
    • Laminated Wall Cladding System

The Installation

This job was to be completed in the end of 2010 and beginning of 2011.

In total we installed:

  • 3262.3m2 of Sureshield Flooring
  • 1153.2 m of Coving
  • Situclad VE was installed to silo bays and tanker bays
Miraka
Miraka
Miraka