Edendale ED4 Powder Tower

The Brief

A new Powder Tower was to be constructed for Fonterra by Ebert Constructions in the year of 2010 and Nuplex Construction was chosen to be part of it.

Ebert Construction was the main contractor to carry out this project.

Industrial Surefloors were contracted by Ebert’s to complete the flooring works on the site.

The Solution

  • Sureshield Flooring
  • Surechem VE Flooring
  • Situclad VE Glass Flake
  • Laminated Wall Cladding System

The Installation

Sureshield was installed over 5 stories including coves and channel drains over an 8 month period.

In total we installed:

  • 6808.88 m2 of Sureshield Flooring
  • 2346.4m of coving
  • Situclad VE Glass Flake to Flume Chambers and Outfall Sumps